Annually organize this event by RSL Ceramics (Private) Limited, by wishing the blessings of Goddess Pattini on the Village and villagers for the continuity of happiness, safety, and harmony. This is a cultural event based on historical stories and people’s believes.

Similar Posts

Soranethota Project – 1.4 MW
Soranethota Mini Hydro-power Project – 1.4 MW Soranethota hydro power project was developed by HPI for Access Energy (Pvt) Ltd. in Badulla. Project was successfully commissioned in December 2008 with the installed capacity of 1.4 MW.

Value Added Tea Sales
By expanding the wings of HPI, now we are into the sales of Value Added Tea which is manufactured in our own Tea Factories. We intend to send samples to Japan, Australia, China, Liberia & Pakistan and waiting to start over our business locally as well as internationally.

Nyamyotsi Project – Stage II
Nyamyotsi Mini Hydropower Project – Stage II Client UNIDO Location Nyadihu District, Republic of Rwanda Capacity [kW] 100 Beneficiaries 250 Households Transmission Voltage 400 V Distribution N/W 3km at 230V Channel Length 200 m Penstock Length 250 m Design Flow 90 Litre/sec Gross Head 120 m Commissioned in July 2012

KalawaAragam 10MW Biomass Power Plant
Construction at KalawaAragam 10MW Biomass Power Plant, Monaragala Client Green Watts (Private) Limited Period Year 2018 ~ 2019 Constructions Carried out Project Cost Chimney Foundation, Flue duct foundation, Heat pipe foundation, Duster platform, Reducer Foundation, Circular pump equipment foundation LKR 11,833,813.00 Canteen Building LKR 10,636,368.59 Retaining Wall construction LKR 5,063,241.95 Hydraulic House, Tilting…

Manakola Project
Manakola Mini Hydro-power Project – 2.5 MW This Project is an idea of Dr. Nanayakkara and his Engineering Team. This Power Plant is located in Hanguranketha DS Division in Nuwara Eliya District and the Water of Beliul Oya, which is a tributary of Mahaweli River, is used near Elamulla village in order to harness renewable…

Kabaragala Project
Kabaragala Mini Hydro-power Project – 2.25 MW Kabaragala Mini Hydro Power project is the maiden turnkey project handled by HPI which is located at the far end of Nuwaraeliya. HPI handled all electro-mechanical and civil works of the project from grass root level and successfully commissioned it in May 2001 with a total generating capacity…